Grid Watch · Week 1

1,358 MW in Kemps Creek

Kemps Creek holds more than a fifth of Sydney's data-centre pipeline.

Map of Kemps Creek showing SYD4 at 1,000 MW, Azure Kemps Creek at 190 MW and Stockland Kemps Creek at 168 MW beside the Mamre and Sydney West substations.

Three campuses off Mamre Road and Aldington Road account for 1,358 of the 6,153 MW we track across Sydney.

AirTrunk's SYD4 on Mamre Road is the largest campus in the Sydney pipeline. The NSW Planning Portal lists it at 1,000 MW. AirTrunk's application documents say 1.2 GW, and we use the portal figure. AirTrunk cut the plan from six buildings to three in an amendment, and the application is in assessment.

Further along Mamre Road, Microsoft handed over the first building of its Azure campus in May 2026 and is building the second. The 190 MW comes from Microsoft's 2021 application. Microsoft hasn't published a newer figure.

Stockland and EdgeConneX's campus on Aldington Road has the Investment Delivery Authority's endorsement and is amending its SEARs. We count it at 168 MW. The portal index cites 245 MW, which we haven't been able to confirm.

  1. SYD41,000 MWAirTrunk · In assessment
  2. Azure Kemps Creek190 MWMicrosoft · Under construction
  3. Aldington Road168 MWStockland and EdgeConneX · Amending its SEARs

Source: NSW Planning Portal, checked 31 October 2026. Disc area on the map is announced campus capacity. Grid: Geoscience Australia, CC BY 4.0.

If a figure here is wrong, email hello@powerhungry.ai and we'll correct it in the next issue.