Marsden Park
Under construction
504MWAnnounced capacity
340MWIT load
10.1haSite area
The site
- Operator
- CDC
- Address
- 105 Hollinsworth Road, Marsden Park
- Lot and DP
- Lot 10 DP1262052
- Site area
- 10.1 ha
- IT load
- 340 MW
- Approved
- 27 November 2025
- Timing
- Commissioning September 2027 to December 2029
- Note
- An application to raise capacity to 743.5 MW is being lodged. It is not yet approved.
Planning
Marsden Park Data Centre
Determination
- SEARs
- Prepare EIS
- Exhibition
- Collate Submissions
- Response to Submissions
- Assessment
- Recommendation
- Determination
158 documents · 4 submissions
1 modification
- Marsden Park Data Centre Modification 1 - Changes to Site Layout Prepare Mod Report
What's nearby
Closest substations
| Vineyard | 330 kV | 7.2 km |
|---|---|---|
| Sydney West | 330 kV | 10.4 km |
| South Marsden Park | 132 kV | 123 m |
| Plumpton | 33 kV | 3.0 km |
| Marsden Park | 132 kV | 3.3 km |
Closest lines
- 330 kV or higher line 415 m
- 132 kV line 3.5 km
Other data centres within 5 km
1 other data centre within 5 km. Sign up free to see which.
Straight-line distances from the site. Connection routes and capacity depend on the network operator.
Grid detail
The full map has the grid detail
Spare capacity, connection queues, planned upgrades, zoning and lots, for any site in NSW. No scores, just the facts to make your own call.
Checked 31 October 2026. Planning stage from the NSW Planning Portal, 2 November 2026. MW is announced campus capacity, not power drawn today.
See every site like this