In planning

551MWAnnounced capacity

Open on the map

The site

Operator
AirTrunk (reported)
Address
Hart Road, Loxford
Timing
On public exhibition
Investment
A$3.7bn reported
Note
Fit-out of an approved industrial building on the former Hydro Aluminium smelter site. The applicant is ADW Johnson; the developer is reported as AirTrunk. Cessnock City Council has objected.

Planning

Kurri Kurri Data Centre

SSD-128819490

Exhibition

  1. SEARs
  2. Prepare EIS
  3. Exhibition
  4. Collate Submissions
  5. Response to Submissions
  6. Assessment
  7. Recommendation
  8. Determination

Construction, fit-out and operation of a data centre with a total power consumption of 550.5 megawatts (MW), located at the former Hydro Aluminium Kurri Kurri plant.

56 documents

What's nearby

CapralKurri1 km
Grid: Geoscience Australia, CC BY 4.0. Square marks are substations.

Location approximate. We have not been able to confirm this site's full boundary.

Closest substations

Newcastle330 kV17.2 km
Waratah West330 kV24.2 km
Capral132 kV296 m
Kurri Kurri132 kV2.6 km
Kurri132 kV2.7 km

Closest lines

  • 330 kV or higher line 573 m
  • 132 kV line 296 m

Straight-line distances from the site. Connection routes and capacity depend on the network operator.

Grid detail

The full map has the grid detail

Spare capacity, connection queues, planned upgrades, zoning and lots, for any site in NSW. No scores, just the facts to make your own call.

See what's in the full map

Checked 2 November 2026. Planning stage from the NSW Planning Portal, 2 November 2026. MW is announced campus capacity, not power drawn today.

See every site like this

Free for your email address. Every other NSW site, the whole planning list and the live map open up.

We use your address to send Power Hungry updates and nothing else. Unsubscribe any time.